Hi Mariano,
Q1: In MRP2 view, i can not find the planning calendar field. I have maintained the planing calender in MRP 1 view as below. Is this OK?
Q2: When i execute MDo4, i am getting below error. How to solve?
Error determining planning periods for calendar TM1
Q3: What do u mean by " you transfer the material to APO, the planning calendar is not going to be transfered. You will need to create a Planning Calendar in APO and load it manually again". ? Do you mean that during material master CIF, the planning calender will not transferred?
Thanks